|
|
||||||||||||||||||||||||||||
|
|
|
General News Developer pushes Paint for sewerage service
MARIANNE - Supervisor Randy Vossburg noted that the Department of
Environmental Protection has approved a revision of the township’s Act 537
plan and that the Paint-Elk Township Joint Sewer Authority can now proceed with
work to correct sewage problems in the River Hill area. Brian W. Huwar attended the recent township meeting and
said that plan is not accurate because it does not include his development
plans, and Act 537 plans by law must include future development. Huwar had
attended the Paint’s Act 537 plan allows for an additional 10
equivalent residential sewer connections each year, based on the average growth
of the township in the past. Huwar was accompanied by his son, Brian D. Huwar who is an
attorney and by Brad Ehrhart of the Clarion County Economic Development
Corporation, but only Brian W. Huwar spoke. Huwar says he asked the township about obtaining nine sewer
tap connections and would like to request 25 more for his development project on
land along But there is no mention of Huwar’s plan in the Act 537
document, and therefore Township officials note that Huwar does not have a formal
plan for developing his land, which would require preliminary approval from the
county planning commission. The township is under a consent order and agreement from
DEP to correct sewage problems in the River Hill area and the Act 537 plan was
one of the required steps. The township submitted a $2.1 million plan for the
corrections that included room for development, but DEP rejected that idea as
enough funding would not likely be available, and officials with PennVEST, a
state agency that funds infrastructure projects with low interest loans,
confirmed that they would not fund the plan. The township then adopted a correction plan costing roughly
half that, but with only limited room for expansion. Huwar said the Rural Utilities Service, part of the federal
Department of Agriculture, might be willing to meet with PennVEST and DEP
officials to discuss funding. Supervisor Ed Bouch said he voted against the original $2.1
million plan and said “I…don’t want to pay for your sewer line.” Huwar said he only wanted the township to build the right
system and “for all of us taxpayers to pay for the right system.” Township secretary Jacqui Blose noted that the customers of
the sewer system, and not the township taxpayers, would pay for the project
through connection and service fees. Huwar said he would also be subject to such fees if his
development were added. Blose noted the consent order and agreement from DEP
requires that the River Hill sewer problems be entirely corrected before the end
of 2009, and that revising the Act 537 plan would mean that deadline could not
be met. “It would take six months (to revise the plan). We
don’t have the luxury of doing that,” she said. Huwar said he spoke with DEP officials at the regional
office in Vossburg said the Paint-Elk Joint Township Sewer Authority
has the final say on the River Hill project and he suggested Huwar attend the
March 13 authority meeting. Trucks still for sale The township still has two trucks for sale. Supervisors
voted to advertise the trucks and they received bids from three different
entities, but none of the bids were acceptable. The largest bid for the 1983 International 10-ton dump
truck with plow and spreader unit was $2,050; and the largest bid for the 2006
Ford F-550 with plow and stainless steel spreader was $28,000. Supervisor Ed Bouch said the bids were too small and
supervisors voted to reject all bids. Bouch moved to try to sell the trucks through a consignment
auction later this spring, and if that fails, to advertise the trucks in Township
News, the publication of the Pennsylvania State Association of Township
Supervisors. Manhole work Supervisors approved a project to upgrade a number of
manholes that are apparently leaking stormwater into the sanitary sewer system. The repairs will be scheduled as a regular maintenance
program. Township secretary Jacqui Blose said the township has the budget to
carry out about $4,000 in manhole maintenance each year. Supervisor Rodger Shingledecker noted that the township is
requiring sewer system customers to replace lateral connections to prevent
stormwater problems, when the township is also causing such problems. The work will require excavation, but Blose said larger
excavating contractors are not interested in such a small project, but Bauer
Excavating and Trucking would be willing to do the work. Supervisors approved Bauer to do the excavation part of the
manhole project. Evergreen Estates Supervisors directed township engineer Ron Kopko to discuss
some road drainage matters with the developers of Evergreen Estates, a housing
development off Vossburg said Kopko, himself and other township officials
and engineers for developer Barry Shinn would meet at the site to do a final
inspection and walk through so the development project could proceed. Vossburg said he wanted to counter some rumors and stated
that the township is not paying Kopko a retainer, and in fact, has not paid him
anything at all so far. Supervisors appointed Kopko as township engineer in
January.
|
| |||||||||||||||||||||||||