The Clarion News Online !


General News

Living Section

Academics Section

Sports


Opinions

Classifieds

The Weather


About Clarion Co.

About Us


The Derrick Online!

 

General News

Sewage system inspection finds improper connections
By Tom DiStefano, Clarion News Writer


CLARION - The effort to find stormwater infiltration in the Clarion Area Authority’s sanitary sewer system continues, and crews have looked at about half of the 900 sewer connections set for inspection.

CAA system manager Lowell Snyder said Robinson Pipe Cleaning is using special cameras to check for leaks, clogs, illegal connections and other problems, and so far has checked 470 sewer laterals – the small pipes that connect homes and businesses to sewer collector lines.

Snyder said engineers were surprised to find about 100 instances where one lateral is connected to another lateral rather than a collector line.

Inspection equipment is designed to run along the inside of a collector line, and send a probe into a lateral line; however, it cannot probe a second lateral from the first lateral.

Laterals feeding laterals can also result in disputes between property owners regarding responsibility for a clog or other problem, Snyder said.

CAA board member Art Aaron noted that property owners are often unaware of the lateral connection problem.

Snyder said the authority should check with legal counsel Keith Pemrick about how to deal with such problems.

The inspections are revealing other problems: about 10 percent of laterals checked so far have downspouts or other stormwater drains connected to the lateral.

Another 20 to 30 laterals checked so far have problems with root clogs, leaky clay tile lines, broken or collapsed tiles and other issues, Snyder said.

Crews are now inspecting laterals in the areas where the worst stormwater infiltration is occurring, and could move into other areas later, Snyder said, though the system could remove most of the stormwater by addressing only the problem areas.

The CAA system is under orders from the DEP to correct stormwater infiltration which is causing the system to overload and release untreated sewage flows into the Clarion River during heavy rains.

Properties with sump pumps, and roof, floor and foundation drains connected to the sanitary system can be required to disconnect such drains and to fix leaks and clogs at the owners’ expense.

Tap request

Snyder said the authority has requested the DEP allow up to 20 new sewer connections. There has been no response form the agency so far, but Snyder said he expects the request to be approved.

The DEP has imposed a ban on new sewer until the overload problems are resolved, but allows a small number of taps to be issued if the system meets DEP requirements.

Snyder said there is a “small waiting list” of people seeking new sewer connections.

Repair work on one of the treatment plant’s clarifier tanks will be re-bid later this month, and that the process should go quickly, Snyder said.

The first attempt at soliciting bids failed when the authority rejected all three bids received; one was late, a second did not have the required bond and the third was unclear.

 

 

 

 

06/10/2008 - Township officials hear advice on prevailing wages, nuisance properties

06/10/2008 - A simple misunderstanding...

06/10/2008 - Clarion will pursue leaf collection grant

06/10/2008 - Knox Twp. seeks supervisor

06/10/2008 - Planning commission OKs Rimersburg projects

06/10/2008 - Navy captain tells local scouts of military experiences

06/09/2008 -

06/09/2008 - Obituaries

06/09/2008 - F.Y.I.


Click Here to Submit a Classified Ad Online.